How to re-count easily for workdays

$
0
0

Hi all,

Please advise for applicable formula that can be use to count the maximum workdays. Below is the guideline and data currently availed. Purpose of request is to optimize the schedule to bear minimum cost (OT, transport, etc) and resource assignment/delivery of my subcontractors. 

Target:: Solve for Min Work Days excluding Holidays and as per below guideline. 

Current Guideline for resource planning via excel of one Project.
--Construction Working Days are from Monday to Saturday ( Sunday is a Regular Non-Working day)
1. if a holiday falls on friday, there is no work <with pay> on the following day (saturday).
2. if a holiday falls on Sunday, there is no work <with pay> on the following day (monday).
3. there is work on monday after "easter Sunday".
4. there is no work <with pay> if the day is between two holidays
5. there is no work <with pay> if the day is between Sunday and a holiday -  eg. 29Dec2014
Note:  Eid’l Fitr and Eid al-Adha : 2 Muslim Holidays to be announced later and to be included in the List of holidays


Start Work Date :20-Jan-14 (Mon)
Tentative End Date :27-Dec-15 (Sun)

List of Holidays
1-Jan-14 (Wed)New Year
31-Jan-14 (Fri)Chinese New Year
25-Feb-14 (Tue)EDSA Revolution Anniversary
9-Apr-14 (Wed)Valor Day
17-Apr-14 (Thu)Maundy Thursday
18-Apr-14 (Fri)Good Friday
19-Apr-14 (Sat)Black Saturday
20-Apr-14 (Sun)Easter Sunday
1-May-14 (Thu)Labor Day
12-Jun-14 (Thu)Independence Day
21-Aug-14 (Thu)Ninoy Aquino Day
25-Aug-14 (Mon)Heroes Day
1-Nov-14 (Sat)All Saints Day
30-Nov-14 (Sun)Bonifacio Day
24-Dec-14 (Wed)Christmas Eve
25-Dec-14 (Thu)Christmas Day
26-Dec-14 (Fri)Special NW day
30-Dec-14 (Tue)Rizal Day
31-Dec-14 (Wed)New Years Eve
1-Jan-15 (Thu)New Year
19-Feb-14 (Wed)Chinese New Year
25-Feb-15 (Wed)EDSA Revolution Anniversary
2-Apr-15 (Thu)Maundy Thursday
3-Apr-15 (Fri)Good Friday
4-Apr-15 (Sat)Black Saturday
5-Apr-15 (Sun)Easter Sunday
9-Apr-15 (Thu)Valor Day
1-May-15 (Fri)Labor Day
12-Jun-15 (Fri)Independence Day
21-Aug-15 (Fri)Ninoy Aquino Day
25-Aug-15 (Tue)Heroes Day
1-Nov-15 (Sun)All Saints Day
30-Nov-15 (Mon)Bonifacio Day
24-Dec-15 (Thu)Cristmas Eve
25-Dec-15 (Fri)Christmas Day
26-Dec-15 (Sat)Addl Special
30-Dec-15 (Wed)Rizal Day
31-Dec-15 (Thu)New Years Eve

The below formulas were extract from year 2006 forum and i am not sure if these can cope up with dynamics of 2 013 xlsx.

=SUM(INT((WEEKDAY(A1-{1,2,3,4,5,6},2)+A732-A1)/7))-(SUMPRODUCT(--(holidays>=start),--(holidays<=end))-SUMPRODUCT(--(WEEKDAY(holidays,2)=7),--(holidays>=start),--(holidays<=end)))

=SUMPRODUCT(INT((MAX(end_date,start_date)-WEEKDAY(MAX(end_date,start_date)+1-{2;3;4;5;6;7})-MIN(end_date,start_date)+8)/7))
-SUMPRODUCT(ISNUMBER(MATCH(WEEKDAY(holidays),{2;3;4 ;5;6;7},0))*(holidays>=MIN(end_date,start_date))*( holidays<=MAX(end_date,start_date)))

--